| Time |
INSTALLER #1
|
|
INSTALLER #2
|
|
| 9:00 |
STEP 3A: Verify Site Readiness
|
STEP 3B: Unload Console and Control Room Lean Cart
|
|
STEP 4A: Cut Out Floor Surface Down to Bare Concrete
|
STEP 4B: Unload and Position the PDU
|
| 9:30 |
STEP 5A: Install Operator Console, Peripherals, Hard Drives, etc.
|
STEP 5B: Start Electrician on PDU Hookup.
Supervise Shippers & Unload All Materials.
|
| 10:30 |
STEP 6: Transport Gantry to Scan Room
|
| 11:00 |
STEP 7: Move Gantry into Final Position. Route Run #52 under Gantry Frame.
|
|
STEP 8: Level the Gantry
|
| 11:30 |
Remove Top and Rear Gantry Covers and Scan Window
|
|
Remove Gantry Dollies
|
|
STEP 9A: Inspect the Gantry Bearing Gap
|
STEP 9B: Install Gantry Alignment Laser and Bracket
|
|
STEP 10: Move Table Into Position
|
| 12:00 |
LUNCH BREAK |
| 1:00 |
STEP 11: Align the Table to the Gantry
|
| 1:15 |
STEP 12: Drill Anchor Holes
|
| 1:45 |
STEP 13A: Anchor the System
|
|
STEP 13B: Remove Shipping Brackets and Table Dollies
|
|
STEP 14A: Install Table Footswitch Assembly
|
STEP 14B: Unroll and Lay Out Cables
|
| 2:30 |
STEP 15: Route Power and Control Cables Between System Components
|
| 3:30 |
STEP 16A: Console Cable Connections (and Finish Console Installation)
|
|
STEP 16B: PDU Cable Connections
|
|
STEP 17A: Gantry Cable Connections
|
| 4:30 |
STEP 18A: Install Customer Options
|
STEP 18B: UPS Installation and Cable Connections
|
|
STEP 19A: Table Cable Connections
|
STEP 19B: System/Site Continuity and Ground Checks
|
| 5:30 |
STEP 20A: Electrical Power Up
|
STEP 20B: Mechanical-Electrical Transition
|
| 6:00 |
|