STEP 3A: Verify Site Readiness

Notice Image
  • notice
  • All sites must have a main disconnect with Lockout/Tagout capability.
  • Non GE-supplied breakers must have/provide under-voltage protection. For more information, refer to the Pre-Installation Manual for this system.
  • A LICENSED ELECTRICIAN shall install and make connections inside the main disconnect.
  1. Lock-out and tag-out the A1 breaker.

  2. Complete inspection to verify site readiness.

  3. Visually inspect the site for damages.