STEP 1: Pre-Delivery Activities
-
Confirm Acceptance to lead installation
-
Confirm Installation Details & Monitor dates with PMI
-
Delivery Date
-
Install Start Date
-
Install Complete D
-
-
Obtain GON and equipment order list
-
Obtain Installation Tools (Refer to Appendix: Installation Tools)
-
Gang Box (JoBox)
-
Alignment Kit
-
Temperature/Humidity meter
-
Electrical Safety Analyzer (Dale 600 Leakage Meter)
-
Nemoto Injector calibration tool
-
Personal Protective Equipment (PPE)
-
Lock-Out Tag-Out devices (LOTO)
-
Digital Level
-
-
Pre-Delivery Site Visit
-
Review Site Drawings with PMI and Customer
-
Surface Penetration permit signed and posted. Otherwise customer performs drilling.
-
Lay Floor Templates and mark the anchoring locations. If JoBox already on-site, then use the hole saw to make floor cutouts.
-
Assess site readiness.
-
Confirm delivery / location of the system with PMI
-
Evaluate cable runs
-
Review the equipment order with PMI
-
Verify order accuracy for correct cable set
-
Meet with Electrician: Set up time for the PDU hookup, and brief electrician on expectations for cutting holes in ducts and removing covers
-
Create System ID’s. De-install old System ID’s if required
-
Initiate IP address and start Broadband checkout process
-
-
Obtain or access appropriate forms
-
Form 2579: HHS - Installations
-
Power & Grounding audit form
-
Electronic Service Reporting (ESR) form: ESR Portal
-
iCenter form: iCenter Portal
-
Site Log Book
-
Review Safety Risk Assessments for Install
-
Competency Form signed-off by FE and manager
-
Contact delivery person to validate time, materials, and manpower
-
Receive equipment at time of delivery
-
Complete Site Readiness Checklist prior to install start
-
Conduct Safety Assessment
-
Complete Surface Penetration Form
-
Audit the JoBox
-
Follow State Approved Shielding Plan, if required
-
Perform Installation Activities