Power on sequencing 2

Prerequisites

Personnel requirements
Required personsPreliminary requirementsProcedureFinalization
1-30 minutes-
Required conditions
ICC Hose Inspection, Coolant Fill, and Coolant Leak Check completed.

About this task

The following provides an overview of each main component in this sequence:

List of Procedures

This document includes the following power on checklist procedures:

  • AC distribution sub breaker on
  • RF power amp sub breaker on
  • Gradient sub breaker on

Procedure

  1. Turn on the switches of the following components in ISC.
    • RF amp
    • KASC chassis
    • GP4
    • PHPS2
    Figure 1. Components switches
  2. Switch the rest of breakers to on according to the following order.
    1. AC distribution sub breaker on
    2. RF power amp sub breaker on
    3. Gradient sub breaker on
  3. Push the EMO Reset SW on.