Power on sequencing 2
Prerequisites
| Personnel requirements | |||
|---|---|---|---|
| Required persons | Preliminary requirements | Procedure | Finalization |
| 1 | - | 30 minutes | - |
| Required conditions |
|---|
| ICC Hose Inspection, Coolant Fill, and Coolant Leak Check completed. |
About this task
List of Procedures
This document includes the following power on checklist procedures:
- AC distribution sub breaker on
- RF power amp sub breaker on
- Gradient sub breaker on