Doing the UPM functional check (head and body)
Do the UPM head and body functional check to make sure the measured RF power is within the expected range.
Prerequisites
| Personnel requirements | |||
|---|---|---|---|
| Required persons | Preliminary requirements | Procedure | Finalization |
| 1 | - | 20 minutes | - |
| Tools and test equipment | |||
|---|---|---|---|
| Item | Quantity | Part number | Manufacturer |
| RF Power Measurement Kit | 1 | Either 5307511-2 or 5307511-3 (Bird wattmeter) | - |
| Safety |
|---|
|
Before working in any GE Healthcare MR suite or performing any GE Healthcare service procedure, you must:
If you have any safety concerns at any time, do not begin work or immediately stop work and move to a safe location. Immediately contact your supervisor or site safety officer for instructions on how to proceed. |
About this task
The UPM functional check runs a prescribed scan in the reflected power chain, using the same test as forward power.
Dual drive RF amplifier systems operate in average power mode. Functional check tests include: 10-second average power check, RF inhibit test, and short-term average power fault host trip test.
Refer to Calibrating RF Amplifier and UPM for calibration information.