Applying LOTO - PGR PDU/Gradient Subsystem
Prerequisites
| Personnel requirements | |||
|---|---|---|---|
| Required persons | Preliminary requirements | Procedure | Finalization |
| 1 | - | 10 minutes | - |
| Tools and test equipment | |||
|---|---|---|---|
| Item | Quantity | Part number | Manufacturer |
| RED Logout Tagout Lock with Each Lock Uniquely Keyed | 1 | 5451778 | - |
| Multi-Locking Device (if multiple service personnel are involved) | 1 | 46-194427P313 | - |
| Red Warning LOTO Tag | 1 | 46-194427P322 | - |
| Digital Voltmeter (DVM) | 1 | 46-194427P284 | - |
| Safety |
|---|
|
Before working in any GE Healthcare MR suite or performing any GE Healthcare service procedure, you must:
If you have any safety concerns at any time, do not begin work or immediately stop work and move to a safe location. Immediately contact your supervisor or site safety officer for instructions on how to proceed. |
| Warning | |
|---|---|
| CAUTION | |
|---|---|
About this task
Note: GE Healthcare supplies two types of MDPs (GE and teal) and two types of PDUs (5140621 and 5343114). The LOTO steps are the same, but the physical components are slightly different. Customers have the option of supplying their own MDPs.
MR750w systems have only the teal MDP (if the MDP is supplied by GE Healthcare) and PDU 5343114.
| Affected by LOTO | ||||
|---|---|---|---|---|
| Name of equipment | Number of locks | Titles of employees authorized to perform LOTO | Titles of affected employees | How to notify |
| All MR equipment | 1 per GE field engineer (FE) | GE Field Engineers | Hospital personnel | Verbal, posted signs |
Note: The following table describes the type, location, and magnitude of energy to be LOTO’d.
| Energy Source | Yes | No | Location of Energy Isolating Means | Magnitude of Energy |
|---|---|---|---|---|
| Electrical | x | PGR PDU circuit breaker panel, Main Disconnect Panel (MDP) circuit breaker panel | 208 VAC, 420 VAC, 380-480 VAC | |
| Pneumatic | x | |||
| Hydraulic | x | |||
| Gas/Water/Steam | x | |||
| Chemical | x | |||
| Mechanical Motion | x | |||
| Gravity | x | |||
| Springs | x | |||
| Thermal | x | |||
| Stored Energy | x | Time discharge of internal capacitors | 208 VAC, 420 VAC | |
| Air Under Pressure | x | |||
| Oil Under Pressure | x | |||
| Water Under Pressure | x | Heat Exchanger Cabinet (HEC), PGR Pump Circuit Breaker (PPMPCB) and RF amp quick disconnect | 5.0 Bar (80 psi) | |
| Gas Under Pressure | x | |||
| Steam | x | |||
| Other | x |
Types of equipment and/or methods selected to dissipate or isolate stored energy
About this task
Type(s) of equipment and/or method(s) used to ensure disconnection(s)
About this task
- A personal lock and tag per Field Engineer (FE) at the site working on the de-energized equipment at the time of LOTO.
- Voltmeter to read voltage for verification that energy has dissipated in the PDU.