MDP power and ground and battery replacement label check
MDP power and ground connections must be tight in order to avoid system failures.
Prerequisites
| Personnel requirements | |||
|---|---|---|---|
| Required persons | Preliminary requirements | Procedure | Finalization |
| 1 | - | 5 minutes | - |
| Safety |
|---|
|
Before working in any GE Healthcare MR suite or performing any GE Healthcare service procedure, you must:
If you have any safety concerns at any time, do not begin work or immediately stop work and move to a safe location. Immediately contact your supervisor or site safety officer for instructions on how to proceed. |
|
Important: GE Field Engineers cannot install, service, or repair the MDP. Only a licensed electrician is qualified to complete those tasks. Refer to the MR Service Safety Manual (5452735) for further safety information.
|
About this task
Overview
MDP power and ground connections must be tight to avoid system failures.
The MDP battery must be replaced by the customer (if batteries are present in system) based on the table below. The MDP battery should be functional to start the cryo-compressor when the system power is restored.
| MDP model | Battery replacement frequency |
|---|---|
| M7000WL | 2 years |
The GE Field Engineer (FE) verifies that the customer completed the MDP PM.