Running dual drive quadrature tool
Procedure
- Click Start for the first iteration.
Scan and analysis begin. It takes about 6 minutes.
- The tool runs up to three iterations, attempting to come to specification.
When the first iteration is complete, calibration results are passed or failed.
- (For passed) Click Quit to complete the calibration. Proceed to Finalization.
Figure 1. Pass case
- If the calibration passes within iteration 3, click Quit to exit the tool.