HUB Replacement

Prerequisites

Procedure

  1. Shutdown application software on the Host computer. Lockout/Tagout power sources. Refer to Lockout/Tagout of the GOC.
  2. Remove the service cover and disconnect ground cable

    Figure 1. Remove the service cover and disconnect ground cable

  3. Remove all cables that are connected to the HUB.
  4. Remove the Velcro tapes from the HUB.
  5. Remove the HUB from the HUB support bracket of GOC.

    Figure 2. Remove Hub

  6. Restore GOC by reverse order of removal.

Finalization

  1. Restore power to the GOC.
  2. Open C Shell and ping ip address in the hospital. Check that result of ping test is ok.
  3. Perform Signal to Noise - Head Scan.