- Topic ID: id_23554370
- Version: 2.0
- Date: Sep 26, 2020 10:12:59 PM
Inverter Gate Command Test (Pro, RT, VCT)
Prerequisites
Overview
The objective of this procedure is to verify that the HV power inverter drive is working properly. No X-Ray is generated in this test. A summary of the procedure follows:
-
Disable HVDC
-
Launch diagnostic tool
-
Run "exposure"
-
Observe results
Procedure
- Remove gantry right side cover.
- Disable HVDC using service switch panel HVDC Enable switch.
- Launch the GENERATOR TOOL.
- Launch the Gate Command Test tool.
- Run the diagnostic. No X-Ray will actually be generated.
Finalization
- If this test fails, your system has an inverter problem.
- If the test passes, the sequence normally dictates that you will move to the Shorted Inverter Test.