- Topic ID: id_11038717
- Version: 3.0
- Date: Jun 10, 2020 2:29:05 AM
NIO16 Host Computer (Z820) NIC Card Replacement
Prerequisites
This procedure shall be followed when replacing the NIC Card in the NIO16 host computer (Z820).
1 Z820 Computer Removal
Procedure
- Shutdown system. Select one of the following methods to Power
OFF the Console:
-
If Applications are up, click on the [Shut Down] button on desktop display and select Shutdown.
-
If Applications are down, open a Terminal Window. Type: halt , then press ENTER.
-
When halt command has finished, power Off the console at the front panel switch.
-
- Apply LOTO. See https://prod-ccms-ge.astoriaondemand.com/astoria/_id_00000018WIA40B59210GYZ_c_Equipment-Service---Lockout-Tagout-PPE_16575359.html#id_19328081 procedure.
- Remove the left side cover from the console.
Refer to Replacement → Console → Console Cover Removal and Installation.
2 NIC Card Replacement
Procedure
- Open the Z820 computer side access panel.
- Remove the Expansion Card Support.
Figure 1. Z820 Airflow Guide and Expansion Card Support

- Disconnect network cable from NIC card. Z820 component location
refer to below Illustration.
Figure 2. Z820 Component Location

- Replace the existing Ethernet NIC card with new one and reconnect the cables.
- Install the Expansion Card Support and close the Side Access Panel.
3 Finalization
Procedure
- Perform the Functional Checks → System Scanning Test instructions from the procedure list.
- Reinstall the console covers.